Nizhnetagilsky Metallurgical Complex ÎOÎ EvrazHolding
Scope of construction works of new water demineralization units (WTP), including desalting plants and soft water plants

Types of equipment configurations of water desalting & softening units

February 2006. Carbon storehouse is the place where water treatment unit will be installed.

May 2006. Site preparation.

May 2006. Excavation site preparation.

June 2006. Start of main building metallic structure installation.

August 2006. Installation of water treatment building skeleton.

September 2006. Installation of water treatment building envelope.

September 2006. Main building gateway.

May 2008. Filtrating section pumping line.

May 2008. Preparation for desalting unit start-up.

May 2008. Water softener in operation.

May 2008. Filtrating section pumping line.